November 1922

Steamboat Building in Elizabeth, PA

A Journal of daily activities at the Elizabeth Marine Ways 1898 to 1925 

November  1922

Home ] Up ] January 1, 1921 ] January 24, 1921 ] February 1921 ] March 1921 ] April  1921 ] May 1921 ] July 1921 ] November 1921 ] January 1922 ] February 1922 ] April  1922 ] May 1922 ] [ November  1922 ] December 1, 1922 ] December 26, 1922 ]

 

 

This journal page has been typed.  To view the actual journal entry click on the image below.

 

October 27, 1922 to November 20, 1922


 

Steamer Ranger Docked October 27, 1922    Wheel chain repairs - Ridge pole over tillers raised up - rudder irons repaired - steam steering gear repaired

The following Barges and Flats Docked & repaired September and November 1922
B 93 - B 53 - 65 - 70 - 36 - 73 - 55 - 30 - 24 - 57
F 1178 - B 70 - 32 F 1134 - Bge 41 - F 1162 - B 60

Sunk Barge 96 Docked & repaired November 14, 1922    put on cradles with Cyclone Digger and Crane Boats #2 and 3

New Pump Boat Hull #1 for the Mines Dept    Set up November 6, 1922   finished November 27, 1922     William Lynch Jr. Foreman

Steamer Voyager   November 13, 1922    Cleaning Boilers - repairs to Boiler deck - Kitchen shelf - wheel guards - 1 new chock - forard Bitts.. And wheel chains

Steamer Beacon    November 15, 1922    repairs to fantails - rudder knockers and tiller couplings pluged and drilled - new pin and bushing for steering bar - key plate riveted - chain brace repaired - Main deck F stairway covers/corners new - rudder irons repaired    Finished eve of the 16th

Steamer J.C. Risher   November 20, 1922    Wheel repaired

October 27, 1922 to November 20, 1922

Click on image to view full page.

      Back Home Up Next